Beachwalk Wastewater Project Almost Completed

WAIKIKI (KHNL) - Work on the Beachwalk Wastewater Emergency Bypass project is about 80% complete.

The project began last May following a major break in a Waikiki wastewater line.

Construction at the makai pit on the corner of Kuhio Avenue and Kaiolu continues.  Workers are building a 20-inch bypass that will serve as an important back-up line.

Later this month, contractors expect to shut down the Beachwalk Pump Station to hook up the bypass line to an existing 42-inch wastewater line and one of the two new lines built through a sophisticated microtunneling process.