HONOLULU (HawaiiNewsNow) -

The state Department of Transportation (DOT) has announced that structural work on the Karsten Thot Bridge in Wahiawa wrapped up Tuesday afternoon.

Since October 19, the bridge has been open to traffic with reduced speeds and traffic control measures in place while crews continued work underneath the structure.

Repairs included the removal and replacement of 4,000 rivets with steel bolts and the replacement of 3,400 pounds of gusset plates under the bridge.

Load limits for the bridge have been returned to the previous 22-ton limit.

Within the next year, additional work to complete anti-corrosive metal coating of the top of the bridge structure will be done.

This work is anticipated to take place primarily during off-peak traffic times, such as at night or on weekends. While not considered part of this emergency work, this type of painting is important to the integrity and life of the steel structure.